LAYING TECHNOLOGY
On level surfaces it is necessary that the breather
pipe coming from the internal room emerges for
31 cm. for any diameters. Lay the first layer
of waterproof membrane, drilling it by the pipe,
heat
the surface that will cover the flange of the
bellows base by flame and lay it.
Lay the second layer of waterproof membrane without
bending it, insert the aerator. In case of tile
roofs, the pipe shall go beyond the border of
the tile hole for at least 30 centimetres, then
the protection and the aerator with a Ø
100 shall be inserted in it.
SPECIFICATION
Supply and laying of steam exhaust aerators for
aeration pipes in bathrooms, kitchens, etc., Ø 100 h.
305 mm. - Ø 125 h. 350 mm. and the relative
bellows base for the
connection to the waterproofing, laid between
two membrane layers.
N.B.: In case of a roof with concrete tiles, the
tile protection is applied instead of the bellows
base.